Guide Underground Drainage

Underground Drainage Installation: Complete Guide

Complete guide to installing underground drainage — trench preparation, pipe laying, gradient, bedding, connections and Building Regulations compliance.

15 March 2025 10 min read

Underground Drainage Installation: Complete Guide

To install underground drainage, you need to excavate a trench at the correct gradient (typically 1:40 for 110 mm foul drains), lay a granular bed, place the pipes with ring-seal joints, backfill with pea gravel surround, connect to the building’s soil stack or gullies, install inspection chambers at changes of direction, and connect to the public sewer or soakaway. The process is straightforward in principle but requires precision — particularly the gradient, which must be consistent to achieve self-cleansing flow. Building Control will inspect the installation before backfilling, so coordination with your local authority is essential.

Underground drainage is one of those jobs where getting it right the first time matters enormously. Once the trench is backfilled and the patio, driveway, or landscaping goes over the top, remedial work means digging it all up again. Taking the time to plan the layout, calculate the gradient, and install properly saves significant money and disruption.


Planning the Layout

What You Need to Know Before You Start

  1. Where the public sewer is — your drain must connect to it (or to a septic tank / cesspit in areas without mains drainage)
  2. The invert level of the sewer — how deep is the connection point?
  3. The distance from the building to the connection — this determines the total pipe run
  4. The gradient — the pipe must fall at the correct rate from building to sewer
  5. Changes of direction — each change needs an inspection chamber or access point
  6. Obstructions — trees, other services (gas, water, electric), hard surfaces, structures

Pre-Start Checks

  • ☐ Building Control notified (if the work requires approval)
  • ☐ Water company consulted (for sewer connection — you may need a Section 106 agreement)
  • ☐ Service search completed (cable, gas, water routes identified)
  • ☐ Trial hole dug to confirm sewer depth
  • ☐ Materials ordered

Tools and Equipment

ToolPurpose
Mini excavator (recommended) or spadesDigging the trench
Laser level or dumpy levelSetting the gradient accurately
Spirit level on a straight edgeChecking gradient in sections
String line and pinsGuide for trench alignment
Tape measure (30 m)Measuring pipe runs
Fine-toothed hacksawCutting PVC-U pipe
File or deburrerSmoothing cut ends
Lubricant (silicone-based)Easing ring-seal joints
Wheelbarrow and compactorMoving and compacting bedding material

Step 1: Excavate the Trench

Trench Dimensions

ParameterMinimumRecommended
WidthPipe diameter + 300 mm450 mm for 110 mm pipe; 600 mm for 160 mm
Depth (under garden/soft area)600 mm cover to pipe crown600–900 mm
Depth (under driveway)600 mm cover (SN4 pipe) or 300 mm (SN8 pipe)600 mm minimum
Depth (under road)1,200 mm cover minimumProject-specific

Gradient

Set the trench bottom at the correct gradient from building to sewer:

Pipe SizeRecommended GradientFall Per MetreFall Per 10m Run
110 mm (foul)1:4025 mm250 mm
110 mm (surface)1:60 to 1:10010–17 mm100–170 mm
160 mm1:60 to 1:8012.5–17 mm125–170 mm

Use a laser level or dumpy level to set the gradient from the building end (high point) to the sewer connection (low point). Mark the gradient on profile boards or stakes at each end of the trench.


Step 2: Lay the Pipe Bed

Why Bedding Matters

The pipe must rest on a consistent, firm bed along its entire length. Resting on hard lumps, rocks, or uneven ground creates point loads that can crack the pipe under backfill pressure.

Bedding Classes (BS EN 1610)

ClassMaterialCompactionUse
Class SConcrete surroundFull encasementUnder roads, heavy loads
Class BSelected granular (pea gravel)Full surround to 150 mm above crownStandard domestic, garden, driveways
Class NNatural trench bottom (if suitable)MinimalOnly where trench bottom is uniform fine material

For most domestic work, Class B bedding is standard:

  1. Spread 100 mm of pea gravel (10 mm) or fine aggregate on the trench bottom
  2. Level and compact lightly
  3. This forms the bed the pipe sits on

Step 3: Lay the Pipe

Starting Point

Start laying from the lowest point (the sewer connection) and work uphill toward the building. This ensures each joint’s socket faces uphill, and any slight misalignment does not create a reverse trap.

Making Joints

PVC-U underground drainage pipe uses ring-seal push-fit joints:

  1. Clean the spigot (plain end) and the socket (bell end)
  2. Check the rubber seal is correctly seated in the socket
  3. Apply silicone lubricant to the spigot end
  4. Push the spigot into the socket until it reaches the insertion mark (moulded line on the pipe)
  5. The gap between the insertion mark and the socket allows for thermal expansion
  6. Check the joint is straight — misalignment causes stress and leaks

Checking Gradient

After laying each section (2–3 pipes), check the gradient:

  • Laser level: Sight along the pipe from the level to the reference mark at the far end
  • Spirit level on a straight edge: Lay a 1.2 m straight edge along the top of the pipe with a spirit level. For 1:40 gradient, a 1.2 m straight edge should show 30 mm of fall

Kalsi’s 110 mm system provides all the pipe lengths and fittings needed for standard domestic runs.


Step 4: Install Inspection Chambers

Building Regulations require access points (inspection chambers or manholes) at:

  • Every change of direction
  • Every junction where branches connect
  • Every significant change of gradient
  • At intervals not exceeding 45 m on straight runs
  • At the head of each drain run (nearest the building)

Inspection Chamber Specification

TypeUse
Mini access chamber (shallow)Straight runs, depths up to 600 mm
Inspection chamberChanges of direction, junctions, depths up to 1,000 mm
ManholeDepths over 1,000 mm, complex junctions

Kalsi’s inspection chambers are available in standard sizes with pre-formed channels and benching.

Installation

  1. Excavate a wider section of trench at the inspection chamber location
  2. Set the chamber base at the correct invert level
  3. Connect incoming and outgoing pipes to the chamber
  4. Build up the chamber shaft with riser sections to ground level
  5. Fit the cover and frame (duty rated for the expected loading — light duty for garden, heavy duty for driveway)

Step 5: Backfill

Surround

After the pipe is laid and inspected:

  1. Haunch the pipe — shovel pea gravel around the sides of the pipe to at least half its height
  2. Cover to 150 mm above the crown with pea gravel or selected fill
  3. Compact gently — do not compact directly over the pipe with heavy machinery

Final Backfill

Above the granular surround:

  1. Backfill with excavated material (free from large stones, rocks, or debris)
  2. Compact in 150–200 mm layers
  3. Fit marker tape (yellow for gas, blue for water — drainage typically does not require tape but good practice to use a marker strip showing “DRAIN BELOW”)

Step 6: Test

Building Control will typically want to inspect the drainage before final backfill. The standard test is:

Water Test

  1. Plug the lower end of the drain
  2. Fill the pipe with water to 1.5 m head above the invert at the upper end
  3. Allow 2 hours for absorption (new pipe stabilising)
  4. Top up to the test mark
  5. Observe for 30 minutes — the water level should not drop by more than 6.4 mm (for 110 mm pipe) per metre of pipe per 30 minutes

Air Test (Alternative)

  1. Plug both ends
  2. Pressurise to 100 mm water gauge (using a hand pump and manometer)
  3. The pressure should not fall to less than 75 mm water gauge within 5 minutes

Step 7: Connect to the Building

Foul Drainage Connection

The underground drain connects to the building’s soil stack via a rest bend at the base of the stack. The rest bend transitions from the vertical soil pipe to the horizontal underground run.

Surface Water Connection

Rainwater downpipes connect to the underground surface-water drain via:

  • Back-inlet gully — a trapped gulley that prevents sewer gases entering the open air
  • Rainwater adaptor — direct connection to the underground pipe (not trapped, as there is no foul-gas risk)

Common Mistakes

MistakeConsequence
Inconsistent gradientPooling, slow flow, blockages
No bedding or inadequate beddingPipe cracks under load
Sharp bends without accessBlockages with no way to rod
Too-shallow coverPipe damage from surface loads
Not testing before backfillingLeaks discovered only after paving is complete
Connecting surface water to foul sewerIllegal in most situations; sewer surcharge risk

Frequently Asked Questions

How to install underground drainage?

Excavate a trench at the correct gradient (1:40 for 110 mm foul), lay a granular bed, place pipes with ring-seal joints, install inspection chambers at every change of direction, backfill with pea gravel surround, test the system (water or air test), and connect to the building and the public sewer or soakaway.

What gradient does a drain pipe need?

For 110 mm foul drains, a gradient of 1:40 (25 mm fall per metre) is recommended. The minimum is 1:80. For surface-water drains, 1:60 to 1:100 is acceptable. For 160 mm pipes, 1:60 to 1:80 is standard. The gradient must achieve self-cleansing velocity (0.7 m/s minimum).

Do I need Building Control for drainage?

Yes, for new drainage installations, alterations to existing drainage, and connections to public sewers. Notify Building Control before starting work. They will inspect the excavated trench and pipe layout before you backfill. Failure to notify can cause problems when selling the property.

How deep should drainage pipes be?

Minimum 600 mm cover (from ground surface to the top of the pipe) under gardens and soft areas. Under driveways, 600 mm minimum with SN4 pipe or 300 mm with SN8 pipe. Under roads, 1,200 mm minimum. Greater depth may be needed to achieve the correct gradient to the sewer.

Can I install drainage myself?

The physical work is within DIY capability for competent homeowners, but the design, gradient calculation, and Building Control process require knowledge. Many homeowners hire a groundworker for the excavation and pipe laying while managing the project themselves. Always notify Building Control and have the work inspected before backfilling.

Related Articles

More from Underground Drainage

Need Technical Advice?

Our team of product specialists can help you find the right solution for your project. Get in touch for expert guidance.