Intermediate Project dependent

Double Embossed External Cladding Installation

Install DuraKlad Double Embossed PVC-U cladding with ventilated battens and concealed stainless-steel mechanical fixings.

Working at Height and Wall Design

Plan and risk-assess all work at height and use suitable access equipment. The supporting wall, battens, wall fixings, membrane, insulation, cavity barriers, flashings and fire suitability must be designed for the building height, exposure, wind load and applicable Building Regulations by competent people.

Product scope

These instructions apply to DuraKlad Double Embossed exterior cladding. Confirm that the boards and matching trims are from the Double Embossed external range before installation.

What You'll Need

Tools

  • Suitable scaffold or working platform
  • Tape measure, pencil and chalk line
  • Spirit level or laser level
  • Drill/driver
  • Fine-tooth saw
  • Nylon hammer
  • Safety glasses and gloves

Materials

  • DuraKlad Double Embossed exterior cladding boards
  • Treated timber battens, minimum 22 x 30mm
  • 70mm-wide battens for corner details
  • 30mm stainless-steel screws or cladding nails
  • Ventilation strip and starter trim
  • Two-part edge and corner trims
  • Matching joiner pieces where required
  • Breathable membrane and insulation where specified

Installation Requirements

Board: 333 x 7mm, 5m long
Material: Cellular PVC-U exterior cladding
Batten size: Minimum 22 x 30mm treated timber
Batten centres: Maximum 300mm, fixed vertically
Fixings: 30mm stainless-steel screws or cladding nails
Expansion: 8mm at each board end
Cavity: 22mm minimum; 30mm with insulation
Ventilation: 22mm clear at the top and bottom
Installation temperature: 5°C to 25°C
Joint: Tongue and groove with matching joiners

Technical basis: the matching product document Double Embossed Cladding Installation Guide, currently hosted by Monster Plastics. Confirm with Kalsi Technical that the boards, trims and revision supplied for the project match this method before installation.

Step-by-Step Installation

1

Store and inspect the boards

Store packaged boards flat and away from direct sunlight so heat cannot build up inside the packaging. Check every board and trim for damage before installation. Do not install below 5°C or above 25°C, and complete each elevation in one continuous installation where practical.

2

Install the treated timber battens

Fix treated timber battens vertically, keeping them level and in a single flat plane. Battens must be at least 22 x 30mm and spaced at no more than 300mm centres. Use battens at least 70mm wide at external and internal corners so the corner can be fixed securely away from the edge of the wall.

3

Provide the ventilated cavity

Maintain uninterrupted vertical ventilation behind the boards. Without insulation, leave a minimum 22mm clear cavity. Where insulation is used, position it behind the battens and leave at least 30mm clear between the insulation and the back of the cladding. Do not pack insulation between the battens or obstruct the airflow path.

4

Fit the ventilation strip and starter trim

Fix the ventilation strip and starter trim together against the face of the battens. Leave 22mm clear below the lowest board and above the highest board for ventilation. Set the bottom batten line 55mm above finished ground level and check that the starter trim is perfectly level before fitting the first board.

5

Prepare edge and corner trims

Install the base sections of the two-part edge and corner trims before the boards. Fix the back of a two-part edging trim at 500mm intervals. Keep trims straight, plumb and positioned so the specified expansion gaps remain available at every board end.

6

Fix through the concealed fixing edge

Use 30mm stainless-steel screws where possible, or 30mm stainless-steel cladding nails. Seat the first board in the starter trim, check it is level, then fix it through the concealed fixing edge at every batten crossing.

7

Allow movement and continue upwards

Leave an 8mm expansion gap at both ends of every board. Engage the next board using the tongue-and-groove joint and tap it fully home along its length with a nylon hammer, taking care not to damage the face. Continue upwards, checking level regularly and fixing each board mechanically at every batten.

8

Join boards and finish the top

Use matching joiner pieces where boards meet along an elevation, maintaining 8mm movement allowance on each side of the joint. Before the final board, fix the top ventilation strip and the base of the finishing profile. Support any cut top edge with a thin treated batten, then snap the trim cover into its base without blocking ventilation.

Critical Checks

Do

  • Keep battens vertical, flat and no more than 300mm apart.
  • Use stainless-steel mechanical fixings at every batten.
  • Maintain 8mm movement allowance at both board ends.
  • Keep the top and bottom ventilation paths open.
  • Use matching trims around corners, windows and doors.

Do Not

  • Do not install outside the 5°C to 25°C temperature range.
  • Do not place insulation between the ventilation battens.
  • Do not block ventilation with sealant, insulation or trims.

Top Edge, Openings and Maintenance

Keep the vertical ventilation route open when finishing below eaves or a drip edge. The drip edge must remain at least 22mm above the ventilation and edge trim and 22mm away from the cladding face.

Use the appropriate starter, edge and corner trims around windows and doors. Continue the same mechanical fixing, expansion and ventilation requirements at every opening.

Clean the installed boards with warm soapy water and a soft brush. Do not use solvent-based cleaners. Periodically check that trims remain secure and ventilation openings are clear.